STAKEHOLDER ENGAGEMENT PROCESS AND PERFORMANCE OF REAL ESTATE PROJECTS IN NAIROBI CITY COUNTY, KENYA

Main Article Content

Alfred Cheruiyot Too
Dr. Ismail Shale Noor

Abstract

Stakeholder engagement is a process by which an organization involves relevant stakeholders who may be affected by the decisions it makes or can influence the implementation of its decisions for a purpose to achieve accepted outcomes. Real estate development, serves as an important contributor to a Nation’s economic growth. It also supports the attainment of society’s essential needs.  The real estate companies in Kenya have also experienced problems with late project completion, subpar quality of completed projects, misuse of client funds, and legal challenges with their clients. The general objective of the study was to establish the effect of stakeholder engagement process and performance of real estate projects in Nairobi City County, Kenya. The specific objectives were to examine effect of plan stakeholder engagement monitor and evaluate stakeholder engagement on performance of real estate projects in Nairobi City County, Kenya. The study adopted a descriptive research design. The unit of analysis was 55 property development companies in Nairobi County.  The unit of observation was the project managers, project supervisors, maintenance managers, and the leasing/renting managers, sales managers hence a total of 275 respondents. A sample of 162 respondents was determined using Yamane 1967 formula. The study used stratified random sampling technique. The study used questionnaires to collect data. A pilot study was carried out with 16 management staff. Content and construct validity were used to validate the instruments. To test reliability of the instrument, the researcher used Cronbach alpha. Data was analyzed using descriptive (frequency, percentage, mean, standard deviation) and inferential statistics (correlation, regression) using SPSS Version 28. According to findings; a strong significant relationship between plan stakeholder engagement and project performance (r=0.933, p=0.000), and a strong significant relationship between monitor and evaluate stakeholder engagement and project performance (r=0.805, p=0.000). The recommendations are that; the project managers should ensure that all identified stakeholders are registered data well captured into the stakeholder registry. The firms should make efforts to employ skilled monitoring and evaluation staff. This will ensure that there is effective monitoring and evaluation of stakeholder engagement.

Article Details

How to Cite
STAKEHOLDER ENGAGEMENT PROCESS AND PERFORMANCE OF REAL ESTATE PROJECTS IN NAIROBI CITY COUNTY, KENYA. (2024). Journal of Applied Social Sciences in Business and Management, 3(2), 137-153. https://grandmarkpublishers.com/index.php/JASSBM/article/view/33
Section
Articles
Author Biographies

Alfred Cheruiyot Too , Jomo Kenyatta University of Agriculture and Technology

Degree of Master of Science in Project Management

Dr. Ismail Shale Noor , Jomo Kenyatta University of Agriculture and Technology

Lecturer

How to Cite

STAKEHOLDER ENGAGEMENT PROCESS AND PERFORMANCE OF REAL ESTATE PROJECTS IN NAIROBI CITY COUNTY, KENYA. (2024). Journal of Applied Social Sciences in Business and Management, 3(2), 137-153. https://grandmarkpublishers.com/index.php/JASSBM/article/view/33

References

Ahmed, A., & Mutundu, J. (2023). The role of M&E systems in shaping public school infrastructure development in Wajir County, Kenya. Journal of Public Administration and Policy Research, 15(2), 78-88.

Akbari, R., Khanzadi, M., & Gholamian, M. R. (2018). The impact of key performance indicators on project success from the stakeholders' perspectives.

Aupe, G., & Sagwa, E. (2020). Influence of stakeholders in project monitoring and evaluation on sustainability of water projects in Kwanza Sub-county.

Bahadorestani, A., Naderpajouh, N., & Sadiq, R. (2020). Stakeholder engagement in sustainability and resilience of infrastructure systems: A comprehensive review. Journal of Cleaner Production, 271, 122195.

Bammer, G. (2021). Monitoring and evaluating stakeholder engagement: Insights for improving project outcomes. Project Management Review, 12(4), 145-158.

Chirau, T., Mapitsa, C., Amisi, M., Masilela, B., & Dlakavu, K. (2020). Stakeholders’ perceptions on the development of a national evaluation system in Africa. African Evaluation Journal, 8(1), 45-59.

Cytonn Investments. (2023). Real estate sector contribution to Kenya’s GDP.

Estate Agents Registration Board (EARB). (2023). Report on real estate scandals in Kenya.

Friedmann, J. (1973). Retracking America: A theory of transactive planning. Anchor Press.

Gupta, A., Crilly, D., & Greckhamer, T. (2020). Stakeholder engagement strategies: Patterns and impact on project success. Academy of Management Journal, 63(1), 123-145.

Hostovsky, C. (2007). The paradox of the rationality of environmental planning: A critique. Environmental Management, 39, 229-248.

Hwang, B. G., Shan, M., & Looi, K. Y. (2019). Sustainable and green project management: Stakeholders’ involvement in construction. Engineering, Construction and Architectural Management, 26(8), 1783-1803.

Hwang, S., & Ng, K. (2021). Effective stakeholder engagement: Strategies for enhancing project performance. Journal of Project Management, 19(2), 134-149.

Innes, J. E., & Booher, D. E. (2010). Planning with complexity: An introduction to collaborative rationality for public policy. Routledge.

Kamau, J. (2019). Challenges facing the real estate sector in Kenya. Kenya Journal of Property Management, 4(1), 12-25.

Karlsen, J. T., Græe, K., & Massie, D. (2022). Trust and transparency in stakeholder engagement: Impacts on project success. International Journal of Project Management, 40(2), 167-177.

Keen, M., & Mahanty, S. (2021). The role of continuous monitoring and review in stakeholder engagement. Stakeholder Management Journal, 10(3), 201-214.

Kenya Property Developers Association (KPDA). (2024). Registered property development companies in Nairobi City County.

Khan, S. (2021). Stakeholder engagement planning and decision-making in large-scale construction projects. Construction Management and Economics, 39(5), 389-402.

Kihuha, M. (2018). Impact of monitoring practices and stakeholder involvement on performance of Global Environment Facility projects in Kenya. Environmental Project Management Review, 7(1), 22-35.

Klaus-Rosinka, M., & Iwko, R. (2021). The role of stakeholder management in project success and sustainability in construction companies. International Journal of Sustainable Development and Planning, 16(7), 1324-1336.

Kotter, J. P. (1996). Leading change. Harvard Business School Press.

Kothari, C. R. (2014). Research methodology: Methods and techniques (3rd ed.). New Age International Publishers.

Kothari, C. R. (2012). The significance of response rates in survey research. Journal of Social Science Research, 18(2), 45-55.

Li, H., Chen, Y., & Liu, Z. (2021). The impact of digital tools on stakeholder engagement in real estate projects. Journal of Digital Innovation in Construction, 8(4), 225-240.

Li, Y., Ng, S. T., & Skitmore, M. (2013). Stakeholder management in construction: A critical review. Construction Management and Economics, 31(2), 89-103.

Luhombo, B. (2022). Effect of stakeholder management process on sustainability of CSR Projects in technical and vocational institutions in Western Kenya. Journal of Corporate Social Responsibility and Environmental Management, 29(5), 311-325.

Magassaouba, M., Kaba, I., & Kamara, A. (2019). Influence of stakeholder engagement on development project performance in Guinea. Journal of Project Management, 9(3), 210-223.

Matyoko, P. (2019). Effectiveness of monitoring and evaluation systems on the sustainability of projects in Tanzania. African Journal of Project Management, 9(3), 210-223.

Matu, M., Kyalo, D., Mbugua, J., & Mulwa, S. (2020). Influence of stakeholder participation in project planning on completion of urban road infrastructure projects in Kenya. International Journal of Project Planning, 11(1), 55-70.

Miles, M. B., & Huberman, A. M. (1994). Qualitative data analysis: An expanded sourcebook (2nd ed.). SAGE Publications.

Ministry of Housing, Land and Urban Development. (2021). Report on the performance of real estate projects in Nairobi County.

Monghasemi, S., Nikoo, M. R., Fasaee, M. A. K., & Adamowski, J. (2015). A novel multi-criteria decision-making model for optimizing time-cost-quality trade-off problems in construction projects. Journal of Civil Engineering and Management, 21(7), 845-855.

Mukundane, G. (2019). Stakeholder management and the decentralization of government projects in Uganda. Public Administration Review, 15(2), 123-138.

Nguyen, H., et al. (2021). The influence of early stakeholder engagement on project time performance. Journal of Construction Engineering and Management, 147(6), 04021057.

Nutt, P. C. (1986). The Theory of Project Implementation. Journal of Management Studies, 23(6), 631-654.

Okazaki, S., Plangger, K., & Menendez, H. (2021). The influence of monitoring stakeholder engagement on large-scale project outcomes. Journal of Strategic Project Management, 29(3), 312-329.

Pal, R., Singh, K., & Mittal, A. (2023). Challenges in managing stakeholder expectations in real estate projects. Real Estate Management Journal, 22(1), 50-65.

Pinto, J. K., & Slevin, D. P. (1987). Critical success factors in effective project implementation. IEEE Transactions on Engineering Management, EM-34(1), 22-27.

Ramezani, A., Khosravi, A., & Ghaderi, A. (2021). Measuring project performance in real estate: Time, cost, quality, and stakeholder satisfaction. International Journal of Real Estate Studies, 20(3), 189-201.

Rogers, P. J. (2019). The role of monitoring in project performance and sustainability. Evaluation and Program Planning, 75, 13-25.

Sachs, S., & Kujala, J. (2021). Stakeholder engagement strategies in complex projects. Business & Society, 60(2), 305-336.

Sedmak, A. (2021). Effective stakeholder engagement planning: Building trust and communication in project management. Project Leadership Review, 9(2), 112-125.

Sibiya, M. M., Aigbavboa, C. O., & Thwala, W. D. (2015). Construction project performance and stakeholder engagement: A review. Procedia Engineering, 123, 72-78.

Talapatra, S., et al. (2019). Stakeholder engagement in Tanzania's public service delivery framework. Journal of Public Administration and Policy Research, 11(3), 54-67.

Tang, L., Shen, Q., & Cheng, E. (2020). Engaging stakeholders for sustainable project delivery in construction. Journal of Cleaner Production, 256, 120345.

World Bank. (2018). Stakeholder Engagement Plan study: Enhancing decision-making through stakeholder involvement. World Bank Publications.

Zaman, S., Ford, M., & Zagt, D. (2023). Stakeholder participation in monitoring and evaluation and its impact on water supply project performance in Australia. Water Resources Management, 37(2), 210-228.

Zou, P. X. W., Zhang, G., & Wang, J. (2021). Managing risks in complex real estate projects: The role of stakeholder engagement. Journal of Construction Engineering and Management, 147(4), 04021023.

Similar Articles

You may also start an advanced similarity search for this article.